Paving to start in Saco

Posted May 16, 2014, at 9:14 a.m.

SACO, Maine — Crews will be paving the Cascade Road, Old Orchard Road and Spring Street in Saco beginning Monday, May 19.

When work is completed on the Cascade Road, the paving operations will move to Old Orchard Road and Spring Street. Motorists should expect lane closures with flaggers assisting in alternating one-way traffic that will last throughout the project’s length.

The exact locations will be on Cascade Road from Route 1 to the Old Orchard Beach town line (0.64 miles). Old Orchard Road from Ferry Road to Timber Oaks Lane (0.4 miles). Spring Street will be from North Street to Lincoln Street (0.45 miles).

It is anticipated all work will be completed by the first week of August.