Lift span from Maine-NH bridge to be removed

Posted Feb. 06, 2012, at 5:21 a.m.
Last modified Feb. 07, 2012, at 5:15 p.m.
Print this   E-mail this    Facebook this   Tweet this     

PORTSMOUTH, N.H. — Demolition crews will wait for daylight to remove the first major component of the 90-year-old Memorial Bridge between Maine and New Hampshire.

Workers had planned to remove the 2-million-pound lift span on Tuesday between 8 p.m. and midnight, but the preparation work is taking longer than expected.

New Hampshire transportation spokesman Bill Boynton says the span will be lifted onto a waiting barge sometime between 8 a.m. and 2 p.m. Wednesday. High tide Wednesday is 11:39 a.m. and Boynton says that time would be optimal if all preparation work is complete.

Federal Highway Administrator Victor Mendez will be on hand to witness the removal and get an update on the bridge replacement project.

A new bridge is expected to open in July 2013.

Similar articles:

Marketplace News

Marketplace

Guidelines for posting on bangordailynews.com

The Bangor Daily News encourages comments about stories, but you must follow our terms of service.

In brief:

  1. Keep it civil and stay on topic
  2. No vulgarity, racial slurs, name-calling or personal attacks.
  3. People who harass others or joke about tragedies will be blocked.

The primary rule here is pretty simple: Treat others with the same respect you'd want for yourself. Here are some guidelines (see more):

ADVERTISEMENT | Grow your business

Marketplace Coupons

ADVERTISEMENT | Grow your business