Greenville negotiates project below budget

Posted Oct. 16, 2008, at 10:25 p.m.

GREENVILLE, Maine — Town officials and a contractor have completed negotiations to bring the Greenville Junction renovation project under budget.

The proposed project now totals $724,750 which will allow uncoated marine-grade steel pilings around a major section of the wharf, riprap in other areas, and a precast retaining wall on a portion of the Wiggins Stream side of the wharf.

Selectmen earlier accepted the lowest bid that was submitted by Wyman and Simpson of Richmond, of $1,499,159. Town officials have about $825,000 available to rehabilitate the rotting wharf. Rather than solicit new bids, selectmen agreed to negotiate with the firm to lower costs, a move seen as acceptable by the town’s attorney and state officials, according to Town Manager John Simko.

A preconstruction meeting will be held next week.

Story continues below advertisement.

Simko said the steel for the project is expected to be delivered the first week in December. printed on October 21, 2016